Fort Lauderdale declares an emergency for the failing Riverwalk seawall; the City says site-securing work could start by mid-December
Fort Lauderdale’s City Manager said Nov. 17 he had declared an emergency for the failing Riverwalk North seawall. See the records, photos and timeline.
Faster ways to steady the Riverwalk North seawall: City precedents and the options it could weigh
City records show faster seawall routes Fort Lauderdale used before, and repair methods the City could weigh for Riverwalk North.
Riverwalk North seawall design contract grew 79.9% to $1,227,735.74 after one change order
City records show the Riverwalk North seawall design contract grew from $682,534.41 to $1,227,735.74 after one change order. Read what the records show.
Riverwalk North seawall design's contract date is now Dec. 5, 2026, two years after its original deadline
The Riverwalk North seawall design contract now runs to Dec. 5, 2026, 730 days late. What City records and reports say on safety, flooding and timing.
Who Is Responsible for the Riverwalk North Design? What the Public Record Shows About Contract P11722
Fort Lauderdale hired HBC Engineering Company in 2023 to design the Riverwalk North seawall. Two lapses, two retroactive revivals and $545,201 later, here is what the City's own documents show about who signed, who manages it, and what we still can't verify.
The $12 Million Riverwalk Collapse: Why Fort Lauderdale Should Look at Marine Startups, Not Just More Concrete
Part of the Riverwalk North catwalk has collapsed and a $12 million rebuild won't start before summer 2027, so here are newer seawall technologies the City should at least weigh, with what's proven and what's still a sales pitch.