Published by Save the Riverwalk, a campaign organized by Nathan Stevenson
Read the short news summary and sign the petition.
A Fort Lauderdale design contract for the failing Riverwalk North seawall now has a maximum fee of $1,227,735.74, up 79.9% from the $682,534.41 the City Commission approved in 2023, according to City records.
The Commission approved the agreement with HBC Engineering Company on Dec. 5, 2023, with a "not-to-exceed" fee of $682,534.41, according to the City's agenda item CAM 23-0852.
The work covers a section of seawall on the New River between the FEC Railway and Andrews Avenue that City staff said in December 2023 "requires immediate replacement," according to the CAM 23-0852 staff memo.
One change order added the money
Change Orders 1 through 4 added no money, according to the City's change order summary in CAM 25-0772.
Change Order No. 5, approved by the Commission on Nov. 4, 2025, added $545,201.33 for additional design scope and added no time, the City's documents show.
That brought the contract total to $1,227,735.74, according to the same records.
The City itemized the change order this way: $409,813.49 to HBC for "adding consultant services," $75,507.84 to GPI Geospatial for survey and test holes, $35,880 to KCI Technologies for landscaping, $18,000 to Tierra South Florida for geotechnical work and $6,000 to Chen Moore & Associates for permitting, according to CAM 25-0772, Exhibit 2.
The City's documents describe the added scope as "stakeholder-requested modifications" and scope "requested by the City and coordinated with stakeholders," but they do not name the stakeholders.
Two retroactive agreements
Twice, the City's own documents say the contract "expired," and each time the City and HBC later signed an agreement made effective from an earlier date, according to CAM 25-0772 and CAM 26-0540.
The first retroactive agreement says the contract "expired on August 2, 2025," and it was approved Nov. 4, 2025, signed Nov. 19, 2025, and added 250 days, those records show.
The second says the first agreement "subsequently expired on April 9, 2026," and it was approved June 2, 2026, signed July 1, 2026, and added 240 days, according to CAM 26-0540.
The City described the second agreement as having "no fiscal impact," according to the CAM 26-0540 staff memo.
City documents give two dates for the first lapse, June 18 and Aug. 2, 2025, and the City later called a related conflict in completion dates "a timeline calculation discrepancy," according to CAM 25-0772 and CAM 26-0540.
The posted record does not show whether work was done or billed during either gap, the campaign's report says.
What the record does not show
The City's posted agenda documents include no invoices or payment records, so they do not show how much of the $1,227,735.74 has been paid, according to the campaign's review as of Nov. 13, 2026.
The campaign asked for invoices and other records under public records request CLK-2789-2026 on Nov. 4, 2026, and as of Nov. 13 none had been produced, with City fee estimates of $1,754.16 and $160.40 outstanding, according to City Clerk's Office emails and campaign records.
No document the campaign reviewed attributes any delay to HBC or evaluates its performance, according to the report.
The design contract is separate from construction, which City staff told WPLG Local 10 on Sept. 28, 2026, would cost $12 million to "replace and reimagine" the seawall from Andrews Avenue to the FEC Railway bridge.
Separately, the City Manager said at the Nov. 17 Conference Meeting that he had declared an emergency for the seawall and started an informal construction-manager-at-risk procurement, with an agreement for the seawall work to come to the Commission later, according to the City's recording of the meeting (2:54:23).
Save the Riverwalk does not allege wrongdoing by the City, HBC or anyone else, and a record not in the posted file may still exist.
Update, Nov. 24, 2026: This article now notes the City Manager's Nov. 17 report that he had declared an emergency for the Riverwalk seawall and started a separate procurement for the work, according to the City's recording of the meeting.
Sources
- City of Fort Lauderdale, CAM 23-0852 (Dec. 5, 2023): staff memo (Background, Resource Impact) and Exhibit 4, the HBC agreement, p. 9.
- City of Fort Lauderdale, CAM 25-0772 (Nov. 4, 2025): staff memo; Exhibit 1, first retroactive agreement; Exhibit 2, Change Order No. 5, pp. 1–2; Exhibit 3, Change Orders 1–4 summary; executed packet, pp. 2–3.
- City of Fort Lauderdale, CAM 26-0540 (June 2, 2026): staff memo; Exhibit 2, second retroactive agreement, p. 1; executed packet, pp. 1, 3.
- WPLG Local 10, Sept. 28, 2026 (published online Sept. 29): local10.com/news/local/2026/09/28/fort-lauderdale-plans-12-million-fix-for-riverwalk-woes/
- City of Fort Lauderdale, Nov. 17, 2026, Conference Meeting, official YouTube recording, City Manager's report from 2:54:23: https://www.youtube.com/watch?v=a0E44CB8TSI&t=10463s. Checked against the audio.
- City Clerk's Office emails to the campaign on request CLK-2789-2026, Nov. 5, 6 and 10, 2026 (not publicly posted; available from the campaign).
- Save the Riverwalk, "The Riverwalk North Seawall Design Contract: What the Public Record Shows, and What It Leaves Out," v3, as of Nov. 13, 2026 (Appendices A and F).
More
- Read the news summary: Fort Lauderdale official calls Riverwalk seawall “a safety concern.” Construction isn’t expected until summer 2027.
- Who is responsible for the Riverwalk North design?
Sign the petition asking the City to fund the fix and set a start date (savetheriverwalk.org/petition)