For City, civic and community leaders

Six specific asks, each backed by the City’s own record.

Our report doesn’t ask for anything new. It asks the City to act on what its staff, its grant applications and its capital plan already say about the Riverwalk North seawall.

Read the short version Download the full report (PDF)

We know the people who serve on the Commission, at City Hall and on civic boards care about the Riverwalk. This page is written for you. Each ask states what we’re requesting, why the record supports it, and who has the authority to act. Every claim links to its source, and our report lists 76 numbered sources. Where the record is unclear or incomplete, we say so.

The project has also changed hands. The November 2025 and June 2026 project memos were issued by City Manager Rickelle Williams, whose separation took effect on July 3, 2026, and Christopher Cooper has been Acting City Manager since that date.[10, 40, 41] A new administration is a good moment to reset the schedule.

At a glance

The six asks in brief

  1. Assess interim stabilization within 30 days, at the October 20 or November 6 meeting, with emergency procurement if the assessment supports it.
  2. Move the money forward. Shift the $7,983,841 programmed for FY 2030 into FY 2027, and bring the $2,967,364 FIND agreement and its match to the Commission by December 2, 2026.
  3. No further design extensions. Hold the December 5, 2026 completion date, publish a construction schedule, and advertise the construction bid in early 2027.
  4. Publish a written plan for the 9/11 Monument, covering storage, how the monument will be honored in the meantime, and a target date for reinstalling the base.
  5. Publish the record: the inspection reports, any post-collapse assessment, the Army Corps permit status, the basis for the $12 million estimate, and monthly updates.
  6. Seek state and federal help. Request a 2027 state appropriation before the session convenes on March 2, 2027, and raise the project with the member of Congress who represents the site from January 2027.

Source: Section 11.2 of our report. See the evidence for each ask.

What, why, and who can act

The asks in full

Our report makes six requests. The first five are directed to the City Commission and the Acting City Manager. The sixth is also directed to the state and federal delegation.

  1. Assess interim stabilization now

    At its October 20 or November 6, 2026 meeting, the Commission should consider a resolution directing the City Manager to have the engineer of record assess interim stabilization of the failed section within 30 days and, if the assessment supports it, to use emergency procurement under Section 255.20 of the Florida Statutes and the City Code.

    Why: The City told a state agency that the catwalk “may be on the verge of collapse,” part of the walkway collapsed by August 12, 2026, and construction is not expected to begin until summer 2027.[5, 6, 7, 13] State law exempts repairs to public works damaged by a sudden, unexpected event that creates an immediate danger, and the City used emergency purchasing for design work on this same seawall in 2017.[57, 26] Whether the collapse meets the legal test is for the City to determine.

    Who can do it: The City Commission, by resolution, and Acting City Manager Christopher Cooper.

  2. Move the money forward

    The Commission should consider a budget amendment moving the $7,983,841 now programmed for FY 2030 into FY 2027, and staff should bring the $2,967,364 FIND agreement and its match to the Commission no later than December 2, 2026.

    Why: The adopted capital plan shows no new funds in FY 2027 through FY 2029, while a summer 2027 construction start falls in FY 2027 and the two FIND awards require $4,000,000 in local match, more than the project’s unspent balance at the end of May 2026.[14, 15, 16, 23] As of October 6, 2026, no agreement for the second award had appeared on a Commission agenda.[20]

    Who can do it: The City Commission, by budget amendment, and the Acting City Manager and City staff, who place the FIND agreement on the agenda.

  3. No further design extensions

    The City should hold HBC Engineering to the December 5, 2026 completion date, publish a construction schedule, and advertise the construction bid in early 2027.

    Why: The design contract has lapsed twice and been revived twice by retroactive agreement, its value has risen by about 80 percent, and its completion date has moved two years.[10, 33]

    Who can do it: The Acting City Manager, who administers the contract, and the City Commission, which approves any changes to it.

  4. A written plan for the 9/11 Monument

    The City should publish how the removed base is being stored, how the monument will be honored in the meantime, and a target date for putting the base back.

    Why: The City removed and stored part of the monument’s base, and no reinstallation date has been published. Under the current schedule, that work would follow a construction start in summer 2027.[8, 13]

    Who can do it: The Acting City Manager, and the City Commission, which can request the plan.

  5. Publish the record

    The City should publish the inspection reports behind its structural findings, including the 2016 survey and the FDOT Bridge Management Inventory System determination, along with any engineering assessment made after the collapse, the status of the Army Corps of Engineers permit, the basis for the $12 million estimate, and monthly progress updates.

    Why: None of these documents is in the public record our report reviewed: the 2016 survey report is not attached, the Corps permit was last described as pending in early 2026, and the record does not contain the basis for the $12 million figure.[25, 15, 23, 13]

    Who can do it: The Acting City Manager and City staff, and the City Commission, which can direct that the documents be released.

  6. Ask the state and federal delegation for help

    The City should seek a 2027 state appropriation through the Broward legislative delegation, including Senator Rosalind Osgood and the members elected to House Districts 99 and 100 in November 2026, before the regular session convenes on March 2, 2027, and should raise the project with the member of Congress who will represent the site from January 2027.

    Why: The project has not appeared in any Resilient Florida statewide plan for 2024 through 2027.[17, 18, 19] Representative Chip LaMarca’s House service ends in November 2026 under the eight-year limit, so the request must go to the delegation that will sit in the 2027 session.[55, 71, 75, 76]

    Who can do it: The City Commission and Acting City Manager, who make the request; Senator Osgood and the House District 99 and 100 members elected in November 2026; and the member of Congress for the site from January 2027, whose district our report could not verify.[70, 73, 74]

These six requests are taken from Section 11.2 of our report.

Following the money

The funding gap

A construction start in summer 2027 falls in FY 2027, but the adopted capital plan shows no new funds until FY 2030, and the two FIND awards require $4,000,000 in local match, more than the project’s unspent balance at the end of May 2026.[14, 15, 16, 23]

Funding sources (Table 4 of our report)[14, 15, 16, 17, 18, 19, 23, 35]
SourceAmountStatusMatch
City CIP P11722, unspent balance (May 31, 2026)$2,937,104Appropriated—
City CIP P11722, FY 2027 – FY 2029$0Adopted plan—
City CIP P11722, FY 2030$7,983,841Programmed, not yet appropriated—
FIND BR-FL-25-172 (2025 cycle)$1,032,636Agreement authorized Feb. 3, 202650% ($1,032,636)
FIND “Part 2” (2026 cycle)$2,967,364Awarded Sep. 24, 2026; agreement pending50% ($2,967,364)
Resilient Florida (DEP)$0Not in 2024-25, 2025-26, or 2026-27 plans—

Written for you

Messages for specific leaders

For the City Commission

You already have the record. What’s missing is a date.

From August 18 through October 6, 2026, no City Commission agenda item carried a title referring to the seawall, although the Commission adopted the capital plan that funds it on September 14.[20, 21] That review covered agenda titles only, not public comment or commissioners’ remarks. The next regular meetings are October 20, November 6, November 17, December 2 and December 15.[52, 53] We’re asking for a resolution on interim stabilization at one of the first two of those meetings, and for the FIND agreement by December 2.

Put the Riverwalk North seawall on the agenda.

For the District 4 office (Vice Mayor Ben Sorensen)

The site is in District 4, and residents are ready to help.

City records place the project in District 4.[10] The Vice Mayor moved the Commission actions on this project in November 2025, February 2026, March 2026 and June 2026.[34, 35, 37, 39] We’d welcome the chance to work with the District 4 office on a public timeline residents can follow.

To reach us, email riva@savetheriverwalk.org. Riva is an AI spokesperson for Save the Riverwalk.

For the Acting City Manager (Christopher Cooper)

A new administration can set a firm schedule.

The design deadline is December 5, 2026.[33] The City has said design will be complete in January and construction will start in summer 2027, but the press reports don’t state the year of that January date, and January 2027 would fall after the contract deadline.[7, 13] A published construction schedule, monthly updates and release of the engineering record would give residents and businesses something solid to plan around.

Publish the schedule and the record.

For the state and federal delegation

A project with state grant support and no state appropriation.

FIND has awarded the project $1,032,636 (2025) and $2,967,364 (September 24, 2026), each requiring an equal local match.[15, 16] The City reported that the Broward County Environmental Resource License was approved on October 3, 2025 and the Florida DEP permit on December 23, 2025, while the U.S. Army Corps of Engineers permit was last described as pending in early 2026.[15, 23] The project doesn’t appear in any Resilient Florida plan for 2024 through 2027.[17, 18, 19] The 2027 regular session convenes March 2, 2027.[75, 76]

Ask the City for its appropriation request, and sponsor it.

Our report did not independently re-verify which state House and congressional districts include the site.

For the Riverwalk Trust and other civic organizations

Stand with your neighbors on the Riverwalk.

The Riverwalk Trust’s board has had a hand in the 9/11 Monument. Representative Chip LaMarca served on the Trust’s board from 2014 to 2018 and co-chaired its 9/11 Monument Committee in 2018.[55] The monument was dedicated by the City on September 11, 2020, and part of its base is now in storage.[8, 22]

Our campaign proposals (these are not recommendations from the report):

  • Endorse the six asks, or the ones that fit your mission, especially Ask 4 (the monument plan) and Ask 5 (publish the record).
  • Share the report with your members and partners.
  • Help residents and businesses along Riverwalk North follow the Commission calendar.

To endorse the asks, email riva@savetheriverwalk.org. Riva is an AI spokesperson for Save the Riverwalk.

What we don’t know yet

Questions the City can answer

We try to be careful about the limits of what we know. The public record we reviewed doesn’t answer these questions, and the City could answer each of them with information it already has:

  • What is the current status of the U.S. Army Corps of Engineers permit?[15, 23]
  • How would a summer 2027 construction start be funded, when the adopted plan shows no new funds until FY 2030?
  • What do the underlying inspection reports say, including the 2016 condition survey and the FDOT Bridge Management Inventory System findings?
  • Will the new wall be built waterward or landward of the existing wall?
  • Has any engineering assessment been made since the August 2026 collapse, and what did it recommend for the interim period?
  • When will the removed portion of the 9/11 Monument base be reinstalled?
  • Did the City ever apply to the Resilient Florida program for this project, and if not, why not?
  • What was the outcome of the City’s 2024 FIND application for $3,000,000?

Source: Section 12 of our report.

The decision record

Who decided

This section lists the formal Commission actions on this seawall and directly related matters, as recorded in the City’s Legistar system. It reproduces Table 5 of our report.

Commission actions of record [21, 24, 25, 27, 29, 30, 31, 34, 35, 37, 39, 49, 50, 51]
DateFileActionResultMoved bySeconded by
Aug. 20, 201313-1042Work Order 3, seawall reinforcement, $77,818ApprovedRobertsDuBose
Oct. 18, 201616-0974Condition survey inspection, up to $9,000ApprovedTrantalisMcKinzie
Oct. 17, 201717-1016Report of $83,404 emergency design purchaseInformational; no vote——
Mar. 19, 201919-0070Reject all bids, ITB 12208-493ApprovedMcKinzieSorensen
Dec. 5, 202323-0852HBC design agreement, $682,534.41ApprovedSturmanGlassman
Jan. 9, 202424-0038Waive competitive solicitation, Las Olas Marina seawall, $2,872,583 (Res. 24-13)AdoptedBeasley-Pittmannot recorded
Mar. 19, 202424-0284FIND application, $3,000,000 (Res. 24-61)AdoptedGlassmannot recorded
Mar. 18, 202525-0345FIND application, $4,000,000 (Res. 25-47)AdoptedBeasley-PittmanGlassman
Apr. 1, 202525-0438Walk-on resolution, FIND application, $4,000,000AdoptedGlassmannot recorded
Nov. 4, 202525-0772First retroactive agreement and CO 5, $545,201.33ApprovedSorensenGlassman
Feb. 3, 202626-0029FIND project agreement, $1,032,636 (Res. 26-26)AdoptedSorensennot recorded
Mar. 3, 202626-0225FIND application, $2,967,364 (Res. 26-39)AdoptedSorensennot recorded
Jun. 2, 202626-0540Second retroactive agreement, 240 daysApprovedSorensenGlassman
Sep. 14, 202626-0670FY 2027-2031 CIP (Res. 26-183)AdoptedGlassmannot recorded

This table reproduces Table 5 of our report. Movers and seconders are as recorded in the City’s Legistar system; “not recorded” means Legistar shows no seconder. Vote tallies are not recorded in the Legistar data reviewed and are not reported here.[21]

Officials relevant to the site

This table reproduces Table 6 of our report.

Officials relevant to the site
OfficeOfficeholderVerification note (from the report)Official contact
City Commission District 4Vice Mayor Ben SorensenCity records place the project in District 4.[10, 66, 67]Official page[66]
BSorensen@fortlauderdale.gov · Office 954-828-5028 (from the City’s website, not in the report[W3])
Acting City ManagerChristopher Cooper (since Jul. 3, 2026)Appointed Jul. 2, 2026.[40, 68]city.manager@fortlauderdale.gov (from the City’s website, not in the report[W4])
Broward County Commission District 8Vice Mayor Robert McKinzieOfficeholder verified; county page describes district as including part of downtown.[69]Official page[69]
Florida Senate District 32Sen. Rosalind OsgoodOfficeholder verified; the site’s district assignment was not independently re-verified.[70]Official page[70]
Florida House District 100Rep. Chip LaMarcaFirst elected 2018; under the eight-year limit his House service ends in November 2026. Site assignment not re-verified.[55, 71]Official page[55]
Florida House District 99Rep. Daryl CampbellOfficeholder verified; the earlier edition placed the site near the HD 99 / HD 100 boundary, which was not re-verified.[72]Official page[72]
U.S. HouseUnverifiedA new congressional map signed in May 2026 redrew Broward districts, and Rep. Moskowitz is running in the new District 25. The district containing the site after January 2027 was not verified.[73, 74]Not listed in the report

The November 2025 and June 2026 project memos were issued by City Manager Rickelle Williams, whose separation took effect on July 3, 2026.[10, 41]