Published by Save the Riverwalk, a campaign organized by Nathan Stevenson
Read the short news summary and sign the petition.
The design to replace a section of Fort Lauderdale's Riverwalk North seawall that City staff said in December 2023 "requires immediate replacement" now has a contract date of Dec. 5, 2026, 730 days after its original due date, according to City records.
CBS Miami reported on Aug. 12, 2026, that City officials expect the final design to be completed by January.
The section runs along the New River between the FEC Railway and Andrews Avenue, according to CAM 23-0852.
A 240-day job, extended five times
The City issued its Notice to Proceed on April 9, 2024, and the contract allowed 240 days, making the work due Dec. 5, 2024, according to CAM 23-0852 and CAM 25-0772.
The due date was extended five times: by 30, 45 and 120 days in Change Orders 2, 3 and 4, by 250 days in a first retroactive agreement and by 240 days in a second, the City's documents show.
Those extensions total 685 days, but the due date moved 730; the 45-day difference equals the gap between the two dates City documents give for the first expiry, June 18 and Aug. 2, 2025, the campaign's report says.
The City's documents cite Florida Power & Light "being unresponsive" to the consultant's requests about pump-outs, the City's decisions on a "Living Seashores" test project, extra pump-out stations "requested by Marine Facilities" and "stakeholder-requested modifications."
The City describes the delays behind Change Orders 2 and 3 as "outside the consultant's control," and no document the campaign reviewed attributes any delay to the design firm.
What the City says about safety
In grant applications to the Florida Inland Navigation District in 2024 and later, the City wrote that the concrete catwalk the seawall supports "may be on the verge of collapse," according to CAM 24-0284, Exhibit 3, and CAM 26-0225, Exhibit 2.
The March 2026 application says the catwalk "has lost all its reinforcement due to corrosion and can no longer sustain the original design load."
That application also calls the catwalk "a public safety hazard" and says the seawall system "retains the subbase for the entire Riverwalk north business area which in the event of a failure, many of these businesses will be impacted."
CBS Miami reported on Aug. 12, 2026, that the City had barricaded the damaged section from Andrews Avenue west to the train bridge.
The City's assistant director of public works told the station, "It is a safety concern, which is why this particular seawall is identified as number two in our replacement plan," adding that "we've added barricades in order to prevent the pedestrians from walking into the danger condition."
Nathan Stevenson, who organizes the campaign, says from his own observation that the Water Taxi stops at the failing section, where riders board and get off.
Standing water and the new wall's height
Stevenson's photos from Sept. 11, 2026, show standing water behind the seawall cap.
The City says the new cap "will be constructed at a 5.0-feet North American Vertical Datum (NAVD) elevation in compliance with City of Fort Lauderdale Ordinance No. C-16-13, which incorporates sea level rise criteria," according to the CAM 26-0225 memo.
Riverwalk Fort Lauderdale's board chair wrote in February 2026 that completing the seawall is "essential to protecting our riverfront from erosion and flooding."
The campaign does not claim the seawall causes flooding; none of the sources it reviewed says so.
When construction could start
The City's March 2026 grant application listed a construction notice to proceed in December 2026, according to CAM 26-0225, Exhibit 2.
In a Sept. 28, 2026, statement to WPLG Local 10, the City said that "as of now, construction is anticipated to begin in summer 2027," and City staff told the station the fix would cost $12 million.
At the Nov. 17 Conference Meeting, the City Manager said he had declared an emergency for the Riverwalk seawall and that work to further secure the site was expected to begin between late November and mid-December, according to the City's recording of the meeting (2:54:23 to 2:55:49); he said he had no end date yet for the project.
Update, Nov. 24, 2026: This article now includes the City Manager's Nov. 17 report that he had declared an emergency for the Riverwalk seawall and expected site-securing work to begin by mid-December, according to the City's recording of the meeting.
Sources
- City of Fort Lauderdale, CAM 23-0852 (Dec. 5, 2023): staff memo, Background; Exhibit 4, p. 40.
- City of Fort Lauderdale, CAM 25-0772 (Nov. 4, 2025): staff memo; Exhibits 1, 2 and 3.
- City of Fort Lauderdale, CAM 26-0540 (June 2, 2026): staff memo; Exhibit 2, p. 1.
- City of Fort Lauderdale, CAM 24-0284 (March 2024): Exhibit 3, FY2024 FIND application, PDF p. 6, signed March 6, 2024.
- City of Fort Lauderdale, CAM 26-0225 (March 2026): staff memo; Exhibit 2, FIND grant application, PDF p. 6 and Attachment E-4 project timeline.
- CBS News Miami, Aug. 12, 2026.
- WPLG Local 10, Sept. 28, 2026 (published online Sept. 29).
- City of Fort Lauderdale, Nov. 17, 2026, Conference Meeting, official YouTube recording, City Manager's report from 2:54:23: https://www.youtube.com/watch?v=a0E44CB8TSI&t=10463s. Checked against the audio.
- Go Riverwalk Magazine, February 2026, "From the Board."
- Photos and Water Taxi observation: Nathan Stevenson, Save the Riverwalk.
- Save the Riverwalk, seawall design contract report, v3, as of Nov. 13, 2026, Findings ("Inconsistent dates") and Appendix B.1.
More
- Read the news summary: Fort Lauderdale official calls Riverwalk seawall “a safety concern.” Construction isn’t expected until summer 2027.
- Who is responsible for the Riverwalk North design?
Sign the petition asking the City to fund the fix and set a start date (savetheriverwalk.org/petition)