Part of the Riverwalk North walkway has collapsed, and the City has barricaded the stretch from Andrews Avenue west to the train bridge (CBS News Miami, Aug. 12, 2026). The City expects the final design by January. It does not expect construction to start before summer 2027 (CBS News Miami), and it now puts the fix at about $12 million (WPLG Local 10, Sep. 28, 2026).

Everything about the rebuild runs through one document: the design contract for City project P11722. We read the contract, its change orders, its two retroactive revivals and the staff memos behind each vote. This article sets out what those records show, who signed and managed each step, and what we still can't verify.

We aren't saying anyone acted improperly. We're asking that a public project be run in public.

The contract

On December 5, 2023, the City Commission voted 5–0 on its consent agenda to approve an agreement with HBC Engineering Company for "Riverwalk North Seawall Replacement Consultant Services." The contract was worth $682,534.41. The City added $60,000 for its own in-house project management, which brought the total to $742,534.41 (CAM 23-0852; Action Summary, Dec. 5, 2023).

HBC is a Florida corporation registered with the state since June 15, 2006 (Florida Division of Corporations).

The scope is the whole design job (Agreement, Exhibit A). It includes:

  • a new sheet-pile seawall
  • removal of the old catwalk
  • fixed and floating docks
  • utility relocation and shore-power pedestals
  • lighting
  • every regulatory permit
  • 60% and 100% design packages, ending in signed and sealed plans
  • bidding support and services during construction

The agreement gave HBC 240 days from the notice to proceed to finish the design and permitting tasks (Agreement). The City issued that notice on April 9, 2024, which set a completion date of December 5, 2024 (CAM 25-0772).

Four change orders, two lapses, two revivals

The first four change orders cost nothing and added time.

  • Change Order 1 (August 2024) reconciled the contract's 240 days with a 375-day task order.
  • Change Order 2 added 30 days. Change Order 3 added 45.
  • The City's change-order summary says those delays came from outside the consultant's control. It cites an unresponsive Florida Power & Light on the pump-outs, and the City still deciding the attachments for a "Living Seashores" test project.
  • Change Order 4 added 120 days so HBC could assess more pump-out stations at the request of the City's marine facilities staff. That moved the deadline to June 18, 2025.

(CAM 25-0772; Change Order summary)

Then the contract lapsed. The City's later agreement states that the original agreement "expired on June 18, 2025" (signed retroactive agreements).

First revival and the cost increase. On November 4, 2025, the Commission voted 5–0 to approve a retroactive agreement and Change Order 5 (CAM 25-0772; Action Summary, Nov. 4, 2025).

  • The revival added 250 days.
  • Change Order 5 added $545,201.33 and took the contract to $1,227,735.74, about 80 percent more than the original award (Change Order 5).
  • Of that increase, $409,813.49 went to HBC. The rest went to the survey, geotechnical and permitting subconsultants, plus $35,880 for a new landscaping subconsultant (Change Order 5).
  • The memo says the extra work came from stakeholder-requested changes (CAM 25-0772):
    • moving the floating dock to the west end
    • raising the pedestrian areas and the 9/11 Monument
    • revising three permit applications
    • updating the benthic report
    • adding a submerged-land survey and 30 utility test holes
    • adding about 120 feet of living seawall

Second lapse and second revival. The first retroactive agreement then expired on April 9, 2026. On June 2, 2026, the Commission voted 5–0 for a second retroactive agreement (CAM 26-0540; Action Summary, June 2, 2026).

  • It added 240 days at no cost and runs to December 5, 2026.
  • The staff memo says it corrects "a timeline calculation discrepancy."

Two years after the original deadline, the design is still not finished.

The City's own documents disagree on key dates

We note these to get the record straight, not to score points. A contract that has lapsed twice needs dates the public can rely on.

  • When the original agreement expired. The second retroactive agreement says June 18, 2025. The first says August 2, 2025 (signed retroactive agreements).
  • When the first revival ended. The November 2025 memo describes a new completion date of February 23, 2026 (CAM 25-0772). The agreement text and the June 2026 memo say April 9, 2026 (CAM 26-0540).
  • When the first revival was approved. The Commission voted on November 4, 2025. Later documents say it was "approved" or "entered" on November 19, 2025 (CAM 26-0540).
  • Change-order dates.
    • Change Order 5's own log dates Change Order 1 as August 7, 2024. Later grant memos say August 29, 2024 (Change Order 5; CAM 26-0029).
    • Change Order 3 is dated January 2 in one place and January 6, 2025 in another.
    • Change Order 5 is dated July 1, 2025 internally but reached the Commission in November.
  • Where the new wall goes. The 2023 agreement puts it in front of, or riverside of, the existing wall (Agreement). The 2026 grant memos describe it as "landward" (CAM 26-0225).

How HBC was selected

The City used a request for qualifications under Florida's Consultants' Competitive Negotiation Act. That law ranks firms on qualifications first and negotiates the fee afterward (RFQ 12716-626; CAM 23-0852).

Responses and shortlist. The RFQ went out on August 11, 2022, and six firms responded by October 12, 2022 (CAM 23-0852):

  • Aptim
  • Cummins Cederberg
  • Dredging & Marine Consultants
  • GHD
  • HBC
  • Lakdas/Yohalem

On February 9, 2023 the City shortlisted three: GHD, HBC and Lakdas/Yohalem. Each firm was scored equally (25 percent each) on firm qualifications, team qualifications, approach to scope, and similar projects and references.

The final scores. After presentations on March 14, 2023, three raters ranked the firms, and lower totals are better (Final ranking).

FirmTotalIrina TokarLouis LafaurieRaymond Nazaire
HBC4.251.251.501.50
GHD4.751.751.501.50
Lakdas/Yohalem9.003.003.003.00
  • Lafaurie and Nazaire scored HBC and GHD the same. The difference came from Tokar's scores.
  • No local or minority-business preference was applied (Final ranking).
  • Raymond Nazaire is the City's Senior Project Manager on P11722 and is listed on every project memo (CAM 23-0852; CAM 26-0540). We note that overlap as a documented fact. It is not unusual for a project manager to sit on a selection committee.
  • The ranking was set in March 2023, and the contract went to the Commission in December 2023.
  • The first-round scoresheets for all six firms are not in the public backup, and neither is the fee negotiation record.

HBC's experience as proposed. HBC's 2022 proposal listed similar seawall and marine projects and references. Most were attributed to individual engineers on its team, such as a seawall in Fort Pierce and boardwalks in Naples, rather than described as HBC contracts (HBC proposal). Qualifications-based selection scores team experience as well as firm experience. HBC's website now features Riverwalk North as a project (HBC Engineering Company).

A second City contract. In July 2026 the Commission also added HBC to a pool of four firms for citywide structural engineering continuing services, which include seawall design (CAM 26-0608).

Who is responsible, as the documents show it

These are the names and roles as they appear in public records. We list business contact routes only where an official document or the firm itself publishes them.

At HBC Engineering Company

  • Adebayo Coker, PE, President. The state corporate filing lists him as President and CEO and as registered agent (Sunbiz).
  • Miguel Villegas, PE. HBC's 2022 proposal named him Project Manager and Structural Engineer (HBC proposal). We could not confirm from public records whether he is still assigned to the project.
  • Engineer of record. The person who seals the final plans isn't named in any public document we found.
  • Contact. HBC publishes info@hbcengineeringco.com and (305) 232-7932 (HBC Engineering Company).

At the City of Fort Lauderdale

  • Project managers. Ana Ziegler, Project Manager II in Public Works, prepared the 2023 award memo and was the original contract contact (CAM 23-0852). Laura De Luca, Project Manager II, is the project manager named in the 2025 and 2026 memos and in the second retroactive agreement (CAM 26-0540; retroactive agreements).
  • Senior Project Manager. Raymond Nazaire is listed on every project memo from 2023 to 2026.
  • Chief Engineer. Jill Prizlee, PE, signed the City's 2024 grant application as project director (FIND Board agenda, June 22, 2024, Item 10.57).
  • Public Works Directors. The agreement makes the Public Works Director the contract administrator (Agreement). Alan Dodd was director in 2023 (CAM 23-0852). Brad Kaine has been director since the 2025 and 2026 actions (CAM 25-0772; CAM 26-0540).
  • City Managers. Greg Chavarria brought the 2023 award (CAM 23-0852). Rickelle Williams signed Change Order 5 and both retroactive agreements, and City Clerk David R. Soloman attested them (retroactive agreements). On the City's October 20, 2026 agenda, Christopher Cooper is listed as Acting City Manager (CAM 26-0928).
  • City Commission. The Commission approved the award and both revivals, each 5–0 on consent.
  • Contact. Public Works is at 101 NE 3rd Avenue, Suite 2100, and the published project manager contact is ldeluca@fortlauderdale.gov, 954-828-5817 (retroactive agreements). Public comment goes to the Commission at its meetings (Save the Riverwalk, Meetings).

What the City knew, and when

The City has been warned about this stretch for years:

  • 2013. The City paid to reinforce the seawall and slab beams because of settling and buckling (CAM 13-1042).
  • 2016. It commissioned a condition survey (CAM 16-0974).
  • March 2019. It rejected both bids for an earlier replacement of this same segment because they came in at about twice the engineer's estimate (CAM 19-0070).
    • A revised version of that memo said staff would consider using the City's annual marina repair contract "to expedite completion of the work." A later revision struck that sentence (first revision; second revision).
    • We found no public record that the City pursued that path, or rebid the work, before the 2022 RFQ.
  • March 2024. The City told the Florida Inland Navigation District that the catwalk "may be on the verge of collapse" and that "the seawall as a whole has become a public hazard" (FIND Board agenda, Item 10.57).
  • 2025. Its $4 million FIND request was cut to about $1.03 million "due to the absence of all required environmental permits by the deadline" (CAM 26-0029).
  • Permits since then. The county and state permits came through in October and December 2025. The Army Corps permit was still pending in March 2026 (CAM 26-0225).
  • 2026 grant. FIND has since awarded $2,967,364 for "Riverwalk North Replacement Part 2" (FIND 2026 awards).

What we could not verify

We want to be clear about the limits of the public record:

  • Whether HBC has delivered the 60% and 100% design packages, and on what dates.
  • How much of the $1.23 million has been invoiced and paid.
  • Who the engineer of record is, and whether the team HBC proposed in 2022 is still assigned.
  • Whether the Army Corps permit has been issued.
  • The basis for the $12 million estimate.
  • The bid amounts and engineer's estimate from 2019.
  • What happened to the project between 2019 and 2022.
  • The outcome of the City's 2024 FIND application.
  • Individual engineering license records. We used the numbers in the firm's own submittals and didn't confirm them on the state licensing site.

None of these documents was in the public backup we reviewed.

Questions for the Commission and staff

  1. Has HBC delivered the 60% and 100% design packages? On what dates, and will they be posted?
  2. The contract lapsed in June 2025 and again in April 2026 before it was revived retroactively. What will make sure the December 5, 2026 deadline holds, with no third revival?
  3. Which date is correct for each lapse and for the first revival? Will the City publish a corrected contract timeline?
  4. Who is HBC's engineer of record, and is the team HBC proposed in 2022 still on the job?
  5. Has the Army Corps permit been issued? If not, what is outstanding?
  6. What is behind the roughly $12 million estimate, compared with the $9 million total project cost in the City's 2024 grant application (FIND Board agenda)?
  7. In 2019 staff floated using the annual marina repair contract to move faster, then dropped the idea. Why, and could a similar route now stabilize the failed section?
  8. Will the new wall be built riverside or landward of the existing wall?

What we are asking

Public records requests we plan to file under Chapter 119, Florida Statutes:

  • The 2019 bid tabulation, both bids, the engineer's estimate, and the drafts of the staff memo that added and then removed the annual-contract language.
  • Any work order under the City's annual marina repair contract for this seawall, and project memos from March 2019 to August 2022.
  • All structural inspections and condition reports for the Riverwalk North seawall and catwalk since 2016, including the 2016 survey.
  • The full scoring record for RFQ 12716-626: all shortlist and final scoresheets, the evaluation committee roster, conflict-of-interest forms, and the fee negotiation memo.
  • Task Order 1, the notice to proceed, signed Change Orders 1 through 4, any approvals to substitute key personnel, all HBC invoices and payments, and the 60%, 90% and 100% design submittals with City comments.
  • Correspondence between City staff and HBC about the 2025 and 2026 lapses and the two retroactive agreements.
  • The Army Corps permit file, and the FIND award and reduction letters for 2024, 2025 and 2026.
  • The cost estimate behind the $12 million figure, and the sealed plan title block naming the engineer of record.

At the November 6, 2026 Commission meeting, we're asking the Commission to consider a resolution directing the City Manager to have the engineer of record assess interim stabilization of the failed section within 30 days. If the assessment supports it, we're asking the City to use emergency procurement. We're also asking the City to:

  • hold the December 5, 2026 design deadline with no further extensions, publish a construction schedule, and advertise the construction bid in early 2027
  • publish the record: inspections, any post-collapse assessment, Army Corps permit status, the basis for the $12 million estimate, and monthly updates

The City Commission moved its November 3 meetings to Friday, November 6, 2026: a conference meeting at 1:00 p.m. and the regular meeting at 6:00 p.m. (Resolution, CAM 26-0834). The City's calendar lists both at the Fort Lauderdale Police Department, Community Room #1004, 1300 West Broward Boulevard (City meeting calendar, checked Oct. 26, 2026). Please check the calendar again before you go. These come from our six asks, and the meeting details are on our meetings page.

If you agree, sign the petition.


Fairness note: This article relies only on public records, which are linked. It doesn't claim that anyone at HBC Engineering Company or the City acted improperly. HBC Engineering Company and City staff are invited to respond, and with their permission we will publish any response in full. Corrections are welcome at riva@savetheriverwalk.org. Riva is the campaign's AI spokesperson, not a person.